Power Supply and Generation Data for 5-April-2008
1. Max. Demand / Energy Catered in Gujarat System.
|
MW FOR |
GSEC |
PVT |
CEN.SEC. |
TOTAL |
TIME |
|
Max. Demand catered in MW |
3127 |
2035 |
2828 |
7990 |
15.00 |
|
Min. Demand catered in MW |
2450 |
1702 |
1986 |
6138 |
1.00 |
|
Energy Catered in MUs |
66.990 |
45.169 |
59.853 |
172.012 |
|
|
Schedule Share |
Central Sector + Bilateral |
46.106 |
|||
2. BILATERAL TRANSACTION DATA IN MUs:
|
Bilateral Sale |
0.000 |
|
Bilateral Purchase |
0.000 |
3. FREQUENCY :
|
Instantaneous Maximum |
Instantaneous Minimum |
Average of the Day |
|
50.46 |
48.98 |
49.96 |
4. DISCOM-WISE ENERGY IN MUs.
|
DISCOM |
JGY |
URB/TWN |
AGR |
IND |
TOTAL |
|
PGVCL |
8.483 |
11.569 |
17.133 |
12.782 |
49.967 |
|
UGVCL |
3.755 |
2.710 |
8.240 |
8.365 |
23.070 |
|
MGVCL |
2.096 |
5.081 |
1.806 |
8.372 |
17.355 |
|
DGVCL |
4.126 |
5.043 |
2.103 |
14.906 |
26.178 |
|
TOTAL |
18.460 |
24.403 |
29.282 |
44.425 |
116.570 |
5. Plant Load Factor and Plant Availability Factor.
|
A |
GSEC ENERGY FOR PLF (EXCLUDING HYDRO) |
64.388 MUS |
|
B |
DAILY PLF |
63.59 % |
|
C |
DAILY PAF |
75.31 % |
|
D |
CUMMULATIVE PLF |
73.39 % |
|
E |
CUMMULATIVE PAF |
81.72 % |
|
F |
AVAILIBILITY FACTOR AT 07.00 HOURS. |
70.22 % |
|
G |
DAILY PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS... |
67.16% |
|
H |
CUMMULATIVE PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS… |
75.42 % |
6. Generation available in MW at 07.00 Hours
GUJARAT |
PLF Thermal |
Hydro |
PVT+(CPP+215 ) |
CEN.SEC(GUJ+DD+DNH) |
Bileteral |
TOTAL GUJARAT |
Tot Total Capacity |
4219 |
547 |
2727 |
* 3001 |
14 |
10185 |
|
Capacity Available |
4219 |
547 |
2727 |
1860 |
14 |
9353 |
|
Planned Outage |
270 |
0 |
78 |
|
|
|
|
Force Outage |
400 |
120 |
98 |
|
|
|
|
Available |
152 |
0 |
436 |
|
|
|
|
Rest Outage |
292 |
276 |
367 |
|
|
|
|
Gen/Flow at 7hrs. |
3105 |
151 |
1748 |
2505 |
14 |
7509 |