Power Supply and Generation Data for 10-April-2008

Home           Past data           Monthly report           Trend           Unit outages 

                       

1. Max. Demand / Energy Catered in Gujarat System.

MW   FOR

GSEC

PVT

  CEN.SEC

TOTAL

TIME

Max. Demand catered  in  MW

3522

2542

2600

8664

15.00

Min. Demand catered   in  MW

3517

2434

   2113

8064

10.00

Energy Catered   in Mus.

84.758

60.414

55.336

200.508

Schedule Share

Central Sector + Bilateral

49.090

 

 

 

 

2. BILATERAL TRANSCATION DATA IN Mus :

Bilateral Sale   

0.000

Bilateral Purchase

0.000

 

3. FREQUENCY :

Instantaneous Maximum

Instantaneous Minimum

Average of the Day.

49.74

48.72

49.11

 

      4. DISCOM-WISE ENERGY IN MUs

DISCOM

JGY

URB/TWN

AGR

IND

TOTAL

PGVCL

9.228

12.092

18.509

12.857

52.686

UGVCL

4.572

3.356

22.498

8.161

38.587

MGVCL

3.836

5.943

3.100

7.417

20.296

DGVCL

4.767

5.467

2.006

16.160

28.400

TOTAL

22.403

26.858

46.113

44.595

139.969

        5.Plant Load Factor and Plant Availability Factor.

A

GSEC ENERGY FOR PLF (EXCLUDING HYDRO)

82.356 MUs

B

DAILY PLF

81.33 %

C

DAILY PAF

86.88  %

D

CUMMULATIVE PLF

75.35 %  

E

CUMMULATIVE PAF

81.73 %

F

AVAILIBILITY FACTOR AT 07.00 HOURS.

86.09 % 

G

DAILY PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS...

81.39 %

H

CUMMULATIVE PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS...

76.43 %

           6.Generation available in MW at 07.00 Hours                  

GUJARAT

Thermal

Hydro

PVT+(CPP+2166 )

CEN.SEC

(GUJ+DD+DNH)

Bilateral

TOTAL

GUJARAT

Total Capacity

4219

547

2727

* 3001

14

10185

Capacity Available

4219

547

2727

2157

14

9650

Planned Outage

270

0

78

 

 

 

Force Outage

120

180

50

 

 

 

Available  

0

0

 0

 

 

 

Restricted Outage

197

215

165

 

 

 

Gen. / Flow 7hrs.

3632

152

2590

2054

14

8428