Power Supply and Generation Data for 13-May-2008
1. Max. Demand / Energy Catered in Gujarat System.
|
MW FOR |
GSEC |
PVT |
CEN.SEC. |
TOTAL |
TIME |
|
Max. Demand catered in MW |
3604 |
2779 |
2616 |
8999 |
15.00 |
|
Min. Demand catered in MW |
3527 |
2465 |
2082 |
8074 |
5.00 |
|
Energy Catered in Mus |
87.066 |
63.809 |
50.942 |
201.817 |
|
|
Schedule Share |
Central Sector + Bilateral |
46.828 |
|||
2. BILATERAL TRANSACTION DATA IN MUs:
|
Bilateral Sale |
6.298 |
|
Bilateral Purchase |
1.375 |
3. FREQUENCY :
|
Instantaneous Maximum |
Instantaneous Minimum |
Average of the Day |
|
50.01 |
48.76 |
49.37 |
4. DISCOM-WISE ENERGY IN MUs.
|
DISCOM |
JGY |
URB/TWN |
AGR |
IND |
TOTAL |
|
PGVCL |
8.950 |
12.235 |
17.233 |
12.978 |
51.396 |
|
UGVCL |
4.812 |
3.414 |
26.074 |
9.133 |
43.433 |
|
MGVCL |
3.137 |
5.967 |
3.394 |
7.881 |
20.379 |
|
DGVCL |
4.792 |
5.089 |
2.117 |
15.041 |
27.039 |
|
TOTAL |
21.691 |
26.705 |
48.818 |
45.033 |
142.247 |
5. Plant Load Factor and Plant Availability Factor.
|
A |
GSEC ENERGY FOR PLF (EXCLUDING HYDRO) |
85.415 MUS |
|
B |
DAILY PLF |
84.35 % |
|
C |
DAILY PAF |
89.75% |
|
D |
CUMMULATIVE PLF |
80.69% |
|
E |
CUMMULATIVE PAF |
81.81 % |
|
F |
AVAILIBILITY FACTOR AT 07.00 HOURS. |
85.09 % |
|
G |
DAILY PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS... |
84.55 % |
|
H |
CUMMULATIVE PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS… |
81.10 % |
6. Generation available in MW at 07.00 Hours
GUJARAT |
PLF Thermal |
Hydro |
PVT+(CPP+215 ) |
CEN.SEC(GUJ+DD+DNH) |
Bilateral |
TOTAL GUJARAT |
To Total Capacity |
4219 |
547 |
2727 |
* 3001 |
14 |
10185 |
|
Capacity Available |
4219 |
547 |
2727 |
2234 |
14 |
9727 |
|
Planned Outage |
200 |
0 |
0 |
|
|
|
|
Force Outage |
120 |
60 |
125 |
|
|
|
|
Available |
0 |
0 |
0 |
|
|
|
|
Rest Outage |
309 |
403 |
-61 |
|
|
|
|
Gen/Flow at 7hrs. |
3590 |
84 |
2663 |
2038 |
14 |
8375 |