Power Supply and Generation Data for 02-March-2009

 

 Home          Past Data         Monthly report           Trend           Unit outage

   

1.        MAX. DEMAND / ENERGY CATERED IN GUJARAT SYSTEM

MW   FOR

GSEC

PVT

CEN.SEC.

TOTAL

TIME

Max. Demand catered in MW.             

2751

1691

2843

7285

7.00

Min. Demand catered in MW    

2594

1887

2321

6802

19.00

Energy Catered   

In MUs.

65.212

42.704

60.601

168.517

 

Central Sector + Bilateral

53.462

      2.    BILATERAL TRANSACTION DATA IN MUs

Bilateral  Sale  

0.450

Bilateral Purchase

9.790

 

3.      FREQUENCY

Instantaneous Maximum

Instantaneous Minimum

Average of the Day

50.02

48.76

49.26

 

4.        DISCOM-WISE ENERGY IN MUs.

DISCOM

JGY

URB/TWN

AGR

IND

TOTAL

PGVCL

8.663

11.809

21.349

11.738

53.559

UGVCL

4.343

3.174

25.914

8.161

41.592

MGVCL

3.348

6.117

3.411

8.016

20.892

DGVCL

4.431

6.150

2.099

18.179

30.859

TOTAL

20.785

27.250

52.773

46.094

146.902

                                                                               

5.        PLANT LOAD FACTOR AND PLANT AVAILABILITY FACTOR

A

GSEC ENERGY FOR PLF (EXCLUDING HYDRO)

  64.626%

B

DAILY PLF

  63.82 %

C

DAILY PAF

  67.35 %

D

CUMMULATIVE PLF

  72.82 %

E

CUMMULATIVE PAF

  81.28 %

F

AVAILIBILITY FACTOR AT 07.00 HOURS.

  65.42 %

G

DAILY PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS...            

  63.92 %

H

CUMMULATIVE PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS…

  73.70 %

 

    6.     GENERATION AVAILABLE IN MW AT 07 Hrs

GUJARAT

Thermal

Hydro

PVT+(CPP+215 )

+ W/M

CEN.SEC(GUJ+DD+DNH)

Bilateral

TOTAL GUJARAT

Total Capacity

4219

547

2727

* 3233

498

10417

Capacity Available

4219

547

2727

2441

498

9934

Planned Outage

820

0

403

 

 

 

Force Outage

315

135

203

 

 

 

Available

45

405

220

 

 

 

Rest Outage

279

5

123

 

 

 

Gen/Flow at 7hrs.

2760

2

1778

2581

498

7121