Power Supply and Generation Data for 29-March-2009

 

 Home          Past Data         Monthly report           Trend           Unit outage

   

1.        MAX. DEMAND / ENERGY CATERED IN GUJARAT SYSTEM

MW   FOR

GSEC

PVT

CEN.SEC.

TOTAL

TIME

Max. Demand catered in MW.             

3473

2350

3348

9171

24.00

Min. Demand catered in MW    

3261

2195

2660

8116

8.00

Energy Catered   

In MUs.

82.288

55.703

67.992

205.983

 

Central Sector + Bilateral (SCH)

59.325

      2.    BILATERAL TRANSACTION DATA IN MUs

Bilateral  Sale  

0.000

Bilateral Purchase

0.000

 

3.      FREQUENCY

Instantaneous Maximum

Instantaneous Minimum

Average of the Day

50.44

49.42

49.97

 

4.        DISCOM-WISE ENERGY IN MUs.

DISCOM

JGY

URB/TWN

AGR

IND

TOTAL

PGVCL

9.295

11.607

20.281

12.510

53.693

UGVCL

4.958

3.429

25.077

9.110

42.574

MGVCL

3.594

6.252

3.364

8.141

21.351

DGVCL

4.843

5.850

2.361

17.292

30.346

TOTAL

22.690

27.138

51.083

47.053

147.964

                                                                               

5.        PLANT LOAD FACTOR AND PLANT AVAILABILITY FACTOR

A

GSEC ENERGY FOR PLF (EXCLUDING HYDRO)

  80.292%

B

DAILY PLF

  79.29%

C

DAILY PAF

  91.35 %

D

CUMMULATIVE PLF

  75.31 %

E

CUMMULATIVE PAF

  81.23 %

F

AVAILIBILITY FACTOR AT 07.00 HOURS.

  78.19 %

G

DAILY PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS...            

  81.02 %

H

CUMMULATIVE PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS…

  75.61 %

 

    6.     GENERATION AVAILABLE IN MW AT 07 Hrs

GUJARAT

Thermal

Hydro

PVT+(CPP+215 )

+ W/M

CEN.SEC(GUJ+DD+DNH)

Bilateral

TOTAL GUJARAT

Total Capacity

4219

547

2730

3412

92

10599

Capacity Available

4219

547

2730

2593

92

10089

Planned Outage

120

0

0

 

 

 

Force Outage

330

60

0

 

 

 

Available

222

405

390

 

 

 

Rest Outage

248

2

195

 

 

 

Gen/Flow at 7hrs.

3299

80

2145

2798

92

8322