Power Supply and Generation Data for 1 May 2007

Home                    Past data                   Monthly report

 

       1. Max. Demand / Energy Catered in Gujarat System.

MW   FOR

GSEC

PVT

  CEN.SEC

TOTAL

TIME

Max. Demand catered  in  MW

3154

2869

1951

7974

15.00

Min. Demand catered   in  MW

3227

2682

1295

7204

18.30

Energy Catered   in Mus.

77.726

55.116

52.133

184.975

Schedule Share

Central Sector + Bilateral

52.787

 

 

 

  2. BILATERAL TRANSACTION DATA IN Mus:

Bilateral Sale   

0.000

Bilateral Purchase

1.510

  3. FREQUENCY :

Instantaneous Maximum

Instantaneous Minimum

Average of the Day.

50.29

48.90

49.48

        4. Average Supply Hours as advice by SLDC Gotri to Agriculture Areas.

UGVCL

8.32

Hours

MGVCL

8.25

Hours

DGVCL

8.23

Hours

PGVCL 

8.23

Hours

Average

8.26

Hours

   5. Plant Load Factor and Plant Availability Factor.

A

GSEC ENERGY FOR PLF (EXCLUDING HYDRO)

        76.114 mus

B

DAILY PLF

         71.74 %

C

DAILY PAF

  85.11 %

D

CUMULATIVE PLF

   84.91 %

E

CUMULATIVE PAF

  80.90%

F

AVAILABILITY FACTOR AT 07.00 HOURS.

 74.11%

G

DAILY PLF OF GSEC UNIT WITH BACKDOWN AND AVAILABLE UNITS IS...

         71.74%

H

CUMULATIVE PLF OF GSEC UNIT WITH BACK DOWN AND AVAILABLE UNITS IS...

 71.76%

         6. Generation available in MW at 07.00 Hours          

GUJARAT

Thermal

Hydro

PVT+(CPP+2166 )

CEN.SEC

(GUJ+DD+DNH)

Bilateral

TOTAL

GUJARAT

Total Capacity

4489

547

2708

2839

151

10223

Capacity Available

4489

547

2708

2344

151

10105

Planned Outage

168

0

0

 

 

 

Force Outage

329

60

           15

 

 

 

Available  

0

0

0

 

 

 

Restricted Outage

537

412

285

 

 

 

Gen. / Flow 7hrs.

3455

75

2425

21893

151

7848