EHV Substation Generating Station EHV Power Line
State Power Utilities Meetings Minutes Schedule Meeting Emloyee Log in e-Urja (ERP) Useful Links

EHV Power Line

EHV LINES PROJECT UNDER GETCO SYSTEM
 
ONGOING EHV LINES PROJECT IN WESTERN REGION
Sr No. Voltage Class Name of Line No of Circuit Date of Completion
( Planned)
Date of Completion
( Actual )
1 765 KV Sipat -Seoni Line –2 S/C Feb-08  
2 400 KV Seoni- Khandwa (Quad) D/C Feb-08  
3 400 KV Nagda-Dehgam D/C Jan-08  
4 400 KV LILO of both ckt. Of SSP-Nagda at Rajgarh D/C Mar-08  
5 400 KV Khandwa-Rajgarh D/C Feb-08  
6 400 KV 315 MVA 400/220 kV ICT-II at Gwalior s/s D/C Mar-08  
7 400 KV LILO of Rourkela- Raipur at Raigarh D/C Dec-07  
8 400 KV Sipat-Raipur D/C Feb-08  
9 400 KV Ranch-Sipat (under ATS of Kahalgaon Ph
II with 40% compensation at Ranchi end)
D/C May-08  
10 220 KV Boisar(PG)- Nalasopara S/C Dec-07  
11 220 KV Bhilad-Vapi (PG) D/C Feb-08  
12 220 KV Vapi(PG)-Kharadpada D/C Mar-08  
13 220 KV Vapi(PG)-Magarwada D/C Mar-08