| PART - B : STATUS OF PETITION FILED BY
APPLICNAT AGAINST SLDC(GETCO) : |
| Sr No |
Petition No & Date |
Filed Before
( Adjudication Body ) |
Applicant Name |
Respondent Name |
Matter/Subject |
Scheduled Hearing |
Status |
| 1 |
1097/2011 |
GERC |
M/s.SAL STEEL Ltd. |
1.SLDC 2.GUVNL |
Application for direction for compliance of the order dtd.18.12.2010 in the Petition No. 1048 of 2010 in the matter of revision
accounting treatment of UI for the Period 30.3.2009 to 21.12.2009, denial of credit of UI charges given to the petitioner
with retrospective effect, recovery of the same by encashment of Bank Guarantee tendered under clause 16(j) of the order
No.3 of 2006 and refund of the said amount, passed against the respondant. |
18/10/2011 at 11:30AM |
Pending |
| 2 |
IA NO. 21 OF 2011 |
Appellate Tribunal For Electricity |
GUVNL |
1.GERC     2.TPLSUGEN   3.SLDC |
|
|
Pending |
| 3 |
IA NO. 22 OF 2011 |
Appellate Tribunal For Electricity |
GUVNL |
1.GERC   2.SAL STEEL Ltd         3.SLDC |
|
|
Pending |
| 4 |
194/MP/2011 |
CERC |
WRLDC |
WR Constituents and Gujarat |
Petition for establishment and maintenance of communication facilities by the USERS of Western Region in terms of
clause 4.6.2 of IEGC,2010 read with clause 5(3) of CEA (Technical Standards for Connectivity to the Grid)
Regulations,2007 to ensure availibility of reliable real time data at WRLDC. |
20/10/2011 10:30hrs |
Pending |