Latest News

Procedure for integration of a new network element of a transmission licensee into the grid and issuance of certificate by Regional Load Despatch Centre (RLDC) for successful trial operation of a transmission element.more

Published Date wise UI/DSM Account Summary (From 1st April onwards 2017) more

SLDC Annual report for year 2016-17.more

Reactive Energy Charges (REC) Account for the week from dt.17.04.2017 to dt.23.04.2017 R0 has been uploaded.more

UI(DEVIATION CHARGES) for the WEEK NO.27(2015-16) from 05/10/2015 to 11/10/2015 REV-2 has been uploaded.more

UI(DEVIATION CHARGES) for the WEEK NO.40(2015-16) from 04/01/2016 to 10/01/2016 REV-1 has been uploaded.more

Invoices for SLDC charges for Oct'17 have been uploaded on SLDC website more

UI(DEVIATION CHARGES) for the WEEK NO.13(2017-18) from 26/06/2017 to 02/07/2017 has been uploaded.more

UI(DEVIATION CHARGES) for the WEEK NO.14(2017-18) from 03/07/2017 to 09/07/2017 has been uploaded.more

Wind Energy Blocked of october-17 for following parties. click for detailsmore

UI(DEVIATION CHARGES) for the WEEK NO.15(2017-18) from 10/07/2017 to 16/07/2017 has been uploaded.more

UI(DEVIATION CHARGES) for the WEEK NO.41(2015-16) from 11/01/2016 to 17/01/2016 REV-2 has been uploaded.more

UI(DEVIATION CHARGES) for the WEEK NO.42(2015-16) from 18/01/2016 to 24/01/2016 REV-1 has been uploaded.more

UI(DEVIATION CHARGES) for the WEEK NO.16(2017-18) from 17/07/2017 to 23/07/2017 has been uploaded.more

UI(DEVIATION CHARGES) for the WEEK NO.17(2017-18) from 24/07/2017 to 30/07/2017 has been uploaded.more

Grid Frequency : 50.013 Hz
     
Gujarat Catered : 11639 MW
Revision : 5
Remarks : ,

Functions

Functions of State Load Despatch Centres as per IEGC 2003.

 

(1) The State Load Despatch Centre shall be the apex body to ensure integrated operation of the power system in a State.

 

(2) The State Load Despatch Centre shall--

 

(a) be responsible for optimum scheduling and despatch of electricity within a State, in accordance with the contracts entered into with the licensees or the generating companies operating in that State;

 

(b) monitor grid operations;

 

(c) keep accounts of the quantity of electricity transmitted through the State grid

 

(d) exercise supervision and control over the intra-State transmission system; and

 

(e) be responsible for carrying out real time operations for grid control and despatch of electricity within the State through secure and economic operation of the State grid in accordance with the Grid Standards and the State Grid Code.

 

(3) The State Load Despatch Centre may levy and collect such fee and charges from the generating companies and licensees engaged in intra-State transmission of electricity as may be specified by the State Commission.

Please contact sldcscada.getco@gmail.com for technical query related to Website Browsing, Downloading, Uploading.....etc.

Company Visiting Hours
16:00 To 18:00

Website Total Visits
18053119

Visitor Graph
Click & View

Website Last Updated
23-11-2017 01:42:40 AM

Supported Browsers